News
-
2026-10-28
Railcare restores track geometry at Erikstad using a trenchless method
On behalf of Infranord, Railcare has carried out a ballast replacement at Erikstad station, south of Mellerud in Dalsland. The work was done to improve track geometry on a section where clay in the track superstructure had affected the track’s stability. “There are a lot of cables in the area, which places high demands on -
2026-05-29
Seven bridges upgraded – Railcare helps boost capacity on the Malmbanan
As part of the extensive work on the Malmbanan, Railcare has carried out ballast replacement on bridges where traditional mechanical solutions cannot be used. This work is a key component of the project led by Infrakraft during 2024–2025 to enable a higher axle load on this heavily trafficked railway. In total, ballast has been replaced